Day 17


Busy day again.  The opening was created for the French doors for the garage conversion.  This created a lot of red brick dust and over powering petrol fumes, but looking good.

The kitchen extension didn’t quite go according to plan as part of the kitchen wall was built using Thermalite blocks and thus as it will be taking a great deal of weight needs to be rebuilt using concrete breeze blocks. This held us back a little bit but it needs doing properly.  The floor level in the garage conversion needed to be determined therefore a hole was drilled to establish the height required.

There were several deliveries today including the insulated plasterboard and scaffolding.

Dsc00196s Dsc00191s Dsc00193s Dsc00194s