It was about 1pm before any work started this afternoon. By the end of the day the outline roof structure had been completed, ready for the roof trusses to go on. In the morning time was spent discussing progress to date, the garage conversion and requirements along with timings for the kitchen. I expressed my reservations as to finishing the work in time for the kitchen being fitted on the 30th, as there is all the decorating to do, moving of pipes and false ceilings as well as tiling the floor. Thus Paul said he would get the blue cupboard pulled out so work could commence.
Thus contents of blue cupboard and garage are now in the dining room, which looks like a bomb site.
Whereas the garage now looks beautifully tidy and organised. This is down to half filling a skip and spending 14 man hours clearing it out on Saturday.