Enya Arrives
We took a while selecting Enya as there were 6 girl puppies to chose from, Amelia, Felicity and Claire all chose a puppy each then Stuart chose one of the three.
Enya
Day 2
Day trip with Reykjavik excursions exploring The Golden Circle.
Day 1
Reykjavik here at last, wanted to visit since 1991! Today done nothing but eat, never eaten so many different foods in one day and some have never eaten ie charr – like salmon, puffin, lamb’s tongue, lemon foam, skyr dessert.
Day 32
Posted by Claire in New Kitchen on April 3rd, 2009
Kitchen fitters arrived and within minutes the kitchen units were in. We decided after recommendation from our builder to have the wall brought forward to bring it in line with the new extension. This is purely cosmetic but worth the extra cost in our opinion.
Security camera fitted at front of property. Even more cabling done and some conduit fitted to hide the wires. If you look carefully at one of these pictures there is a jelly dummy hiding in the saw dust.
Day 31
Posted by Claire in New Kitchen on April 3rd, 2009
Outside render completed. Internal damp proof screed applied to kitchen wall. sockets moved to cater for TV lift mechanism. Pipe work buried in boiler room. Other kitchen wall patched and skimmed. Security camera fitted at rear. Lots more network cable fitted.
Day 30
Posted by Claire in New Kitchen on April 2nd, 2009
A bit more plastering was done and rendering to the outside. The tiles were laid and grouted as far as possible due to the fact that the whole in the boiler cupboard still needs filling in in order to complete the tiling. the boiler and pipes are now done and the under floor heating was tested.
Day 29
Posted by Claire in New Kitchen on March 31st, 2009
French doors are installed and more of the soffits replaced.
The landing window is boarded up and the window taken away to be resized.
The kitchen is almost totally re plastered and the new boiler connected. However, there is still more work to be done with regards to the new pipe work.
Kitchen door is taken away to be altered so it hangs the other way
Day 27
Posted by Claire in New Kitchen on March 28th, 2009
Floor screed is laid. Work commenced approx 8.15 and was finished before lunch. Should be totally firm by Monday am. The rest of the day more work was done outside on the soffits etc.
Day 26
Posted by Claire in New Kitchen on March 27th, 2009
The floor insulation is put down and then the red plastic is then placed on top. The pipe is then laid out as per the map provided by Polypipe which is calculated to give the correct BTU rating. Also today the soffits etc where removed from the exterior of the whole house.
Day 25
Posted by Claire in New Kitchen on March 26th, 2009
Second coat of smooth render is applied.
The plaster board makes such a difference to the overall look of the room. It is starting to take shape.
Day 24
Posted by Claire in New Kitchen on March 25th, 2009
Kitchen floor goes down and further electrics are installed both for hardwired network and kitchen lights and sockets.
Day 23
Posted by Claire in New Kitchen on March 24th, 2009
A start to the network cables being installed.
Sand laid down and preparations for the concrete base to be poured in the kitchen with some more electrics done.
First coat of render to extension.
Day 22
Posted by Claire in New Kitchen on March 23rd, 2009
Day 21
Posted by Claire in New Kitchen on March 20th, 2009
Part of the render on original part of the house is removed ready for new leadwork
The earth moved, well some of it , i.e. the kitchen floor. A few cracks have appeared in the shower room and back room due to the hammering and removing of the kitchen wall, hopefully these are superficial. Decorator called round and we discussed what was required for the kitchen in terms of wallpapering and paint.
Day 20
Posted by Claire in New Kitchen on March 19th, 2009
Velux goes in, should give plenty of light.
More of the kitchen floor is dug up and finally the wall comes tumbling down, well perhaps is knocked down brick by brick. It is now easier to visualise just how the new kitchen will look and gives a better idea of the size. The steel is now in place.
Day 19
Posted by Claire in New Kitchen on March 18th, 2009
A bit more of the garage completed with a ceiling going in. The kitchen floor is broken up and the steel beam is put in.
Day 18
Posted by Claire in New Kitchen on March 17th, 2009
By the end of today we looked as if we were ready to demolish the house, given the scaffolding surrounding the whole building. I was surprised at the amount of work involved in erecting the scaffolding and how heavy it was. The kitchen window was now in.
Internally a new wall had been built and Acro props were holding up the ceiling, it all looked rather precarious. Some electrics had also been done in the new extension.
The garage had also new electrics installed as well as a floor.
Again 4 vans and about 8 men at maximum capacity today.
Day 17
Posted by Claire in New Kitchen on March 16th, 2009
Busy day again. The opening was created for the French doors for the garage conversion. This created a lot of red brick dust and over powering petrol fumes, but looking good.
The kitchen extension didn
My party.
It is a swimming party
At:Bamber bridge leisure centre
time:4:50 to 7:00
DO NOT LOSE THIS!
Day 16
Posted by Claire in New Kitchen on March 14th, 2009
Day 15 – Friday the 13th
Posted by Claire in New Kitchen on March 13th, 2009
Day 14
Posted by Claire in New Kitchen on March 12th, 2009
Garage door has now gone and they have made some wooden beams for kitchen ceiling
Roof is now felted and battened. In the kitchen the floor tiles have been removed as has the coving.
Day 13
Posted by Claire in New Kitchen on March 11th, 2009
Lots of men on site today doing the roof, progress made today in terms of fascia boards etc and velux
Day 12
Posted by Claire in New Kitchen on March 10th, 2009
More of the roof completed ready for felting and tiling, should be completed Friday. Discussions re under floor heating, electric velux
Day 11
Posted by Claire in New Kitchen on March 9th, 2009
It was about 1pm before any work started this afternoon. By the end of the day the outline roof structure had been completed, ready for the roof trusses to go on. In the morning time was spent discussing progress to date, the garage conversion and requirements along with timings for the kitchen. I expressed my reservations as to finishing the work in time for the kitchen being fitted on the 30th, as there is all the decorating to do, moving of pipes and false ceilings as well as tiling the floor. Thus Paul said he would get the blue cupboard pulled out so work could commence.
Thus contents of blue cupboard and garage are now in the dining room, which looks like a bomb site.
Whereas the garage now looks beautifully tidy and organised. This is down to half filling a skip and spending 14 man hours clearing it out on Saturday.
Day 10
Posted by Claire in New Kitchen on March 6th, 2009
Today 8.15 builders were on site. The guys who were knocking out the landing window also arrived putting down lots of polythene to protect everything. Unfortunately after removing the glass it was evident that the window could not simply be moved up several courses of brickwork, keeping it intact. What happens next is still to be decided. Tom arrived to discuss various aspects and talk to Les from Kam design. We discussed the size of the patio, quoting for soffits and barge boards for the rest of the rear of the house. Paid the 2 invoices and gave Tom a large list of things to find out about. By 2pm ish all the building work was completed and work stopped for the day. The plan is to discuss window options on Monday when Paul returns to work. We gave go ahead for Garage conversion to start next week so will be busy clearing out garage this weekend.
Day 9
Posted by Claire in New Kitchen on March 5th, 2009
Finished off tying block work into existing wall. Put in RSJ and completed doorway opening, moved soil pipe. Wood arrived ready for wall plates.
My party.
Today it is not my birthday party.
But it is not a lot of days off.
So i am excited of going to it.
It is only on the 21st of march.
Day 8
Posted by Claire in New Kitchen on March 4th, 2009
Day 7
Posted by Claire in New Kitchen on March 3rd, 2009
The slab was prepared and checked by Planning Officer. The slab has made a great base for the outdoor swimming pool- lol. It has rained for most of the day and has started to fill up with rainwater.
watching films on my laptop .
Me and my sis watched two very good films called Igor and fly me to the moon. They are both reccomended by me. Hope you watch them and have a nice day.
Day 6
Posted by Claire in New Kitchen on March 2nd, 2009
my weekend
I went to my dads we went for a long bike ride .It was fun . we went to Botany bay just to have a look.
Day 5
Posted by Claire in New Kitchen on March 1st, 2009
By 10 am still no sign of the builders. Rang Tom who said would get Paul to ring me. Received a call saying one of the workforce hadn
Day 4
Posted by Claire in New Kitchen on February 26th, 2009

Arrived 8.20am. Today they have cemented round all the drains and started building some of the walls of the new extension. Tomorrow is the slab going down.



Day 3
Posted by Claire in New Kitchen on February 26th, 2009

No Kevin today, Yarik arrived 9.00. On my return lots of pipework had been resited for the drains and concrete poured into the foundations.
Day 2
Posted by Claire in New Kitchen on February 26th, 2009
Building inspector called and approved foundations although suggested we underpinned part of the corner of existing building – we agreed at extra cost. Large delivery arrived of blocks, sand , cement etc.
Day 1
Posted by Claire in New Kitchen on February 26th, 2009
Plumber called round at the weekend, filling us with confidence that the build was going ahead as plannned.
Before the work started
Posted by Stuart in New Kitchen on February 26th, 2009

Before the build started